Ender Schedule
Project Start Date: 12/1
Project Finish Date: 8/11
Tasks
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | M1, M2 | 35 days | 12/1 | 1/18 | | 100% |
| 2 | Infrastructure I | 15 days | 12/1 | 12/21 | | 100% |
| 3 | Transaction System | 15 days | 12/1 | 12/21 | Kin | 100% |
| 4 | IRange Implementation | 10 days | 12/1 | 12/14 | Akkana,Jfrancis | 100% |
| 5 | Text Selection (Part 1) | 15 days | 12/29 | 1/18 | Mjudge | 100% |
| 6 | Basic Transactions | 10.5 days | 1/4 | 1/18 | | 100% |
| 7 | Change Attribute (add, remove, modify) | 2 days | 1/4 | 1/5 | Buster | 100% |
| 8 | Insert String | 1 day | 1/6 | 1/6 | Buster | 100% |
| 9 | Delete Range in Text Element | 2 days | 1/7 | 1/8 | Buster | 100% |
| 10 | Delete Element | 1 day | 1/11 | 1/11 | Buster | 100% |
| 11 | Split Element | 3 days | 1/12 | 1/14 | Buster | 100% |
| 12 | Join Element | 2 days | 1/14 | 1/18 | Buster | 100% |
 
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 13 | M3 | 27 days | 1/19 | 2/24 | | 100% |
| 14 | Infrastructure II | 25 days | 1/19 | 2/22 | | 100% |
| 15 | Text Selection (Part 2) | 15 days | 1/19 | 2/8 | Mjudge | 100% |
| 16 | Content Model to Stream | 5 days | 1/19 | 1/25 | Kostello[20%] | 100% |
| 17 | Editing API | 5 days | 2/16 | 2/22 | Buster | 100% |
| 18 | Keyboard Navigation | 5 days | 1/19 | 1/25 | | 100% |
| 19 | Move Selection Left, Right by 1 char | 1 day | 1/19 | 1/19 | Mjudge | 100% |
| 20 | Move Selection Above, Below by 1 line | 4 days | 1/20 | 1/25 | Mjudge | 100% |
| 21 | Advanced Selection | 5 days | 2/9 | 2/15 | | 100% |
| 22 | Extend Selection (shift) | 5 days | 2/9 | 2/15 | Mjudge | 100% |
| 23 | Basic Editing Commands | 12.5 days | 1/19 | 2/4 | | 100% |
| 24 | Delete Range | 5 days | 1/19 | 1/25 | Buster | 100% |
| 25 | Copy | 5 days | 1/19 | 1/25 | Kostello[20%] | 100% |
| 26 | Paste Plain Text | 2 days | 2/2 | 2/4 | Akkana | 100% |
| 27 | Messenger Enhancements | 23 days | 1/25 | 2/24 | | 100% |
| 28 | Plain Text Mode | 10 days | 1/25 | 2/10 | Sfraser | 100% |
| 29 | Consult w/ Messenger Team to embed Ender | 2 days | 2/23 | 2/24 | Mjudge | 100% |
| 30 | Basic Caret (In Text) | 10 days | 1/25 | 2/5 | | 100% |
| 31 | Mac | 10 days | 1/25 | 2/5 | Sfraser | 100% |
| 32 | Win | 2 days | 1/25 | 1/26 | Sfraser | 100% |
| 33 | Unix | 2 days | 1/25 | 1/26 | Sfraser | 100% |
 
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 34 | M4 (April 6) | 11 days | 3/22 | 4/5 | | 100% |
| 35 | Advanced Caret (Everywhere) | 9 days | 3/22 | 4/1 | | 100% |
| 36 | Mac | 3 days | 3/22 | 3/24 | Sfraser | 100% |
| 37 | Win | 3 days | 3/25 | 3/29 | Sfraser | 100% |
| 38 | Unix | 3 days | 3/30 | 4/1 | Sfraser | 100% |
| 39 | Spell Checking | 10 days | 3/22 | 4/2 | | 100% |
| 40 | API | 3 days | 3/22 | 3/24 | Kin | 100% |
| 41 | XP Support Methods | 5 days | 3/25 | 3/31 | Kin | 100% |
| 42 | Enable INSO (need to sync with ns tree) | 2 days | 4/1 | 4/2 | Kin | 100% |
| 43 | Keyboard Navigation | 1 day | 3/22 | 3/22 | | 100% |
| 44 | Move Selection Left, Right by 1 char | 1 day | 3/22 | 3/22 | Mjudge | 100% |
| 45 | Insert Element | 8 days | 3/23 | 4/1 | | 100% |
| 46 | Insert Image | 4 days | 3/23 | 3/26 | Akkana | 100% |
| 47 | Insert Link | 4 days | 3/29 | 4/1 | Akkana | 100% |
| 48 | Editing Commands | 6 days | 3/22 | 3/29 | | 100% |
| 49 | Apply Bold, Italic, Underline | 3 days | 3/22 | 3/24 | Buster | 100% |
| 50 | Remove Bold, Italic, Underline | 3 days | 3/25 | 3/29 | Buster | 100% |
| 51 | Toolbar Support For Mail/News Compose | 2 days | 4/2 | 4/5 | Sfraser | 100% |
 
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 52 | M5 (April 27) | 11 days | 4/6 | 4/20 | | 100% |
| 53 | International Support | 1 day | 4/6 | 4/6 | | 100% |
| 54 | Stream text using source document charset | 1 day | 4/6 | 4/6 | Kostello[20%] | 100% |
| 55 | Implement WP-like typing rules | 5 days | 4/6 | 4/12 | Jfrancis | 100% |
| 56 | GUI (Dialogs, Toolbars) | 4 days | 4/13 | 4/16 | | 100% |
| 57 | Image Properties | 3 days | 4/13 | 4/16 | Cmanske | 100% |
| 58 | Editing Commands | 11 days | 4/6 | 4/20 | | 100% |
| 59 | Change Structure | 5 days | 4/6 | 4/12 | Buster | 100% |
| 60 | Apply/Remove Font Face | 3 days | 4/13 | 4/15 | Buster | 100% |
| 61 | Apply/Remove Font Size | 3 days | 4/16 | 4/20 | Buster | 100% |
| 62 | Apply/Remove Font Color | 1 day | 4/6 | 4/6 | | 100% |
| 63 | Find/Replace (infrastructure) | 5 days | 4/6 | 4/12 | Sfraser | 100% |
| 64 | Select All | 1 day | 4/6 | 4/6 | | 100% |
 
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 65 | M6 (May 18) | 22 days | 5/3 | 6/1 | | 0% |
| 66 | International Support | 3 days | 5/3 | 5/5 | | 0% |
| 67 | Stream text using alternate charset | 1 day | 5/3 | 5/3 | Kostello[20%] | 0% |
| 68 | Pasteboard -- Unicode encoding | 1 day | 5/4 | 5/4 | Kostello[20%] | 0% |
| 69 | Pasteboard -- Local System Code Page | 1 day | 5/5 | 5/5 | Kostello[20%] | 0% |
| 70 | Find | 8 days | 5/3 | 5/12 | | 0% |
| 71 | Find (forwards, backwards, case sensitive) | 3 days | 5/3 | 5/5 | Sfraser | 0% |
| 72 | Find Dialog | 5 days | 5/6 | 5/12 | Sfraser | 0% |
| 73 | Save | 2 days | 5/6 | 5/7 | | 0% |
| 74 | Save (HTML Document Only) | 1 day | 5/6 | 5/6 | Kostello[20%] | 0% |
| 75 | Save As.. (HTML Document Only) | 1 day | 5/7 | 5/7 | Kostello[20%] | 0% |
| 76 | Editor Ownership Model | 3 days | 5/3 | 5/5 | Mjudge | 0% |
| 77 | GUI (Dialogs, Toolbars) | 10 days | 5/3 | 5/14 | | 0% |
| 78 | Hook Up XP Save Dialog through XUL | 2 days | 5/13 | 5/14 | Sfraser | 0% |
| 79 | Use dialog to save off document | 1 day | 5/10 | 5/10 | Kostello[20%] | 0% |
| 80 | Paragraph Properties | 3 days | 5/3 | 5/5 | Cmanske | 0% |
| 81 | Character Properties | 3 days | 5/6 | 5/12 | Cmanske | 0% |
| 82 | Find & Replace | 2 days | 5/17 | 5/18 | | 0% |
| 83 | Replace | 1 day | 5/17 | 5/17 | Sfraser | 0% |
| 84 | Find/Replace Dialog | 1 day | 5/18 | 5/18 | Sfraser | 0% |
| 85 | Spell Checking/Text Services | 10 days | 5/3 | 5/14 | | 0% |
| 86 | Modify Unix makefiles to work with INSO | 4 hrs | 5/3 | 5/3 | Kin | 0% |
| 87 | Modify Mac build system to work with INSO | 4 hrs | 5/3 | 5/3 | Kin | 0% |
| 88 | FirstSelectedBlock, LastSelectedTextBlock | 3 days | 5/4 | 5/6 | Kin | 0% |
| 89 | Design SpellChecker Service COM interface | 2 days | 5/7 | 5/10 | Kin | 0% |
| 90 | Spell Check Dialog | 3 days | 5/10 | 5/13 | Cmanske | 0% |
| 91 | Personal Dictionary Dialog | 1 day | 5/14 | 5/14 | Cmanske | 0% |
| 92 | Investigate issues for making Ender the plain text replacement | 3 days | 5/3 | 5/5 | Buster | 0% |
| 93 | Mail/News Support | 18 days | 5/3 | 5/26 | | 0% |
| 94 | Stream in HTML | 3 days | 5/3 | 5/5 | Akkana | 0% |
| 95 | Wrapping Support | 3 days | 5/19 | 5/21 | Sfraser | 0% |
| 96 | Message Quoting Support | 3 days | 5/24 | 5/26 | Sfraser | 0% |
| 97 | Editing Commands | 22 days | 5/3 | 6/1 | | 0% |
| 98 | Make Bulleted List | 3 days | 5/3 | 5/5 | Jfrancis | 0% |
| 99 | Make Numbered List | 1 day | 5/6 | 5/6 | Jfrancis | 0% |
| 100 | Convert Bullet/Numbered List to Paragraphs | 3 days | 5/7 | 5/11 | Jfrancis | 0% |
| 101 | Decrease Indent | 3 days | 5/12 | 5/14 | Jfrancis | 0% |
| 102 | Increase Indent | 3 days | 5/17 | 5/19 | Jfrancis | 0% |
| 103 | Change Alignment | 2 days | 5/20 | 5/21 | Jfrancis | 0% |
| 104 | Insert Target | 4 days | 5/17 | 5/20 | Cmanske | 0% |
| 105 | Insert Table | 4 days | 5/21 | 5/26 | Cmanske | 0% |
| 106 | Insert Rule | 4 days | 5/27 | 6/1 | Cmanske | 0% |
| 107 | IME Support | 3 days | 5/11 | 5/13 | | 0% |
| 108 | Ongoing consulting w/ Tague | 3 days | 5/11 | 5/13 | Kin | 0% |
| 109 | Clipboard | 7 days | 5/6 | 5/14 | | 0% |
| 110 | Insert HTML | 6 days | 5/6 | 5/13 | Akkana | 0% |
| 111 | Paste HTML | 1 day | 5/14 | 5/14 | Akkana | 0% |
| 112 | Selection | 1 day | 5/6 | 5/6 | | 0% |
| 113 | Up/Down Arrow Behavior | 1 day | 5/6 | 5/6 | Mjudge | 0% |
 
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 114 | M7 (June 8) | 40 days | 5/24 | 7/16 | | 0% |
| 115 | Keyboard Navigation | 1 day | 5/24 | 5/24 | | 0% |
| 116 | Up/Down Arrow Key Support | 1 day | 5/24 | 5/24 | Mjudge | 0% |
| 117 | Drag & Drop | 11 days | 5/24 | 6/7 | | 0% |
| 118 | Drag and Drop Hooks | 2 days | 5/24 | 5/25 | Akkana | 0% |
| 119 | Image | 2 days | 5/26 | 5/27 | Akkana | 0% |
| 120 | Link | 2 days | 5/28 | 5/31 | Akkana | 0% |
| 121 | Text | 2 days | 6/1 | 6/2 | Akkana | 0% |
| 122 | HTML Fragment | 3 days | 6/3 | 6/7 | Akkana | 0% |
| 123 | Mouse Event Handling | 7 days | 5/27 | 6/4 | | 0% |
| 124 | Context Menu Hookup (Except Tables) | 7 days | 5/27 | 6/4 | Sfraser | 0% |
| 125 | Resize hooks | 1 day | 6/2 | 6/2 | Cmanske | 0% |
| 126 | MouseMove event hooks | 1 day | 6/3 | 6/3 | Cmanske | 0% |
| 127 | GUI (Dialogs, Toolbars, etc.) | 16 days | 6/4 | 6/25 | | 0% |
| 128 | Color Properties | 5 days | 6/7 | 6/11 | Sfraser | 0% |
| 129 | Toolbar | 5 days | 6/14 | 6/18 | Sfraser | 0% |
| 130 | Color Picker | 4 days | 6/4 | 6/9 | Cmanske | 0% |
| 131 | Select Edit Changes | 1 day | 6/10 | 6/10 | Cmanske | 0% |
| 132 | Extra HTML | 1 day | 6/11 | 6/11 | Cmanske | 0% |
| 133 | H Rule Properties | 1 day | 6/14 | 6/14 | Cmanske | 0% |
| 134 | Font Menu | 1 day | 6/15 | 6/15 | Cmanske | 0% |
| 135 | Link Properties | 5 days | 6/21 | 6/25 | Sfraser | 0% |
| 136 | Remove Link Warning | 0.5 days | 6/16 | 6/16 | Cmanske | 0% |
| 137 | Edit Page | 19 days | 6/8 | 7/2 | | 0% |
| 138 | Hook Up Menu Item | 2 days | 6/28 | 6/29 | Sfraser | 0% |
| 139 | Load URL into Editor | 1 day | 6/8 | 6/8 | Akkana | 0% |
| 140 | Add Edit Page Dialog | 1 day | 6/30 | 6/30 | Sfraser | 0% |
| 141 | Open Page Dialog | 2 days | 7/1 | 7/2 | Sfraser | 0% |
| 142 | Menu Item Support | 10 days | 7/5 | 7/16 | | 0% |
| 143 | Menus and menubar | 2 days | 7/5 | 7/6 | Sfraser | 0% |
| 144 | Menu command handling, dialog hookup | 4 days | 7/7 | 7/12 | Sfraser | 0% |
| 145 | Menu command state maintenance | 4 days | 7/13 | 7/16 | Sfraser | 0% |
| 146 | IME Support | 5 days | 5/25 | 5/31 | | 0% |
| 147 | Optimizing for speed and debugging | 5 days | 5/25 | 5/31 | Mjudge | 0% |
| 148 | Ender in Gecko | 11 days | 5/24 | 6/7 | | 0% |
| 149 | Enable Ender as Plain Text Field | 3 days | 5/24 | 5/26 | Buster | 0% |
| 150 | Enable Ender as Plain Text Area | 3 days | 5/27 | 5/31 | Buster | 0% |
| 151 | Enable Ender as Rich Text Area | 5 days | 6/1 | 6/7 | Buster | 0% |
| 152 | Basic Table Editing | 17 days | 6/16 | 7/9 | | 0% |
| 153 | New Table Properties Dialog | 3 days | 6/16 | 6/21 | Cmanske | 0% |
| 154 | Insert Row | 1 day | 6/21 | 6/22 | Cmanske | 0% |
| 155 | Insert Column | 3 days | 6/22 | 6/25 | Cmanske | 0% |
| 156 | Insert Cell | 1 day | 6/25 | 6/28 | Cmanske | 0% |
| 157 | Delete Row | 1 day | 6/28 | 6/29 | Cmanske | 0% |
| 158 | Delete Column | 3 days | 6/29 | 7/2 | Cmanske | 0% |
| 159 | Apply Background Color | 1 day | 7/2 | 7/5 | Cmanske | 0% |
| 160 | Table Properties | 2 days | 7/5 | 7/7 | Cmanske | 0% |
| 161 | Cell Properties | 2 days | 7/7 | 7/9 | Cmanske | 0% |
 
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 162 | M8 (June 29) | 35 days | 6/14 | 7/30 | | 0% |
| 163 | Editing Commands | 4 days | 6/14 | 6/17 | | 0% |
| 164 | Insert Style sheet | 3 days | 6/14 | 6/16 | Buster | 0% |
| 165 | Remove Style sheet | 1 day | 6/17 | 6/17 | Buster | 0% |
| 166 | Other | 35 days | 6/14 | 7/30 | | 0% |
| 167 | Disable Links | 2 days | 6/14 | 6/15 | Jfrancis | 0% |
| 168 | Disable Javascript | 3 days | 6/14 | 6/16 | Akkana | 0% |
| 169 | Templates | 5 days | 6/14 | 6/18 | Kostello[20%] | 0% |
| 170 | Performance work | 10 days | 7/19 | 7/30 | Sfraser | 0% |
| 171 | Insert Unknown Tag | 5 days | 7/9 | 7/16 | Cmanske | 0% |
 
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 172 | M9 (July 20) | 3 days | 7/5 | 7/7 | | 0% |
| 173 | Handle Form Elements Gracefully | 3 days | 7/5 | 7/7 | Buster | 0% |
| 174 | I18N | 2 days | 7/5 | 7/6 | | 0% |
| 175 | LANG attribute support | 2 days | 7/5 | 7/6 | Kostello[20%] | 0% |
| 176 | Arrow Key To Next/Prev Unicode Code Point | 1 day | 7/5 | 7/5 | Mjudge | 0% |
| 177 | Selection | 2 days | 7/6 | 7/7 | | 0% |
| 178 | Double Click to select word | 1 day | 7/6 | 7/6 | Mjudge | 0% |
| 179 | Triple Click To select block | 1 day | 7/7 | 7/7 | Mjudge | 0% |
 
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 180 | Post 5.0 Deliverables | 13 days | 7/26 | 8/11 | | 0% |
| 181 | Composer Shell | 5 days | 8/5 | 8/11 | Sfraser | 0% |
| 182 | Publishing | 10 days | 7/26 | 8/6 | | 0% |
| 183 | Review UE Design | 6 days | 7/26 | 8/4 | Cmanske,Sfraser,Jglick | 0% |
| 184 | Implement Publishing Dialog | 5 days | 7/29 | 8/4 | Cmanske | 0% |
| 185 | Publish Document Core Code | 10 days | 7/26 | 8/6 | Kin | 0% |
|
|
 |